Hydro Works
Ended
| Year | Action | Detail | Cost | Result |
|---|---|---|---|---|
| 1911 | Advance | 24 months | - | success |
| 1909 | Advance | 6 months | - | success |
| 1909 | build_wire_line | - | $5 | success |
| 1909 | build_wire_line | - | $5 | success |
| 1909 | build_wire_line | - | $100 | success |
| 1909 | build_wire_line | - | - | failed |
| 1909 | build_wire_line | - | - | failed |
| 1909 | build_wire_line | - | - | failed |
| 1909 | Build Coal Power | (40, 20) | $3,000 | success |
| 1909 | Build Coal Power | (38, 24) | - | failed |
| 1909 | Advance | 12 months | - | success |
| 1908 | build_wire_line | - | $20 | success |
| 1908 | build_wire_line | - | $15 | success |
| 1908 | build_wire_line | - | - | failed |
| 1908 | build_wire_line | - | - | failed |
| 1908 | Build Power Line | (38, 22) | - | failed |
| 1908 | Build Power Line | (35, 22) | - | failed |
| 1908 | Build Power Line | (37, 22) | - | failed |
| 1908 | Build Power Line | (27, 22) | - | failed |
| 1908 | Build Power Line | (25, 22) | - | failed |
| 1908 | Build Power Line | (15, 22) | - | failed |
| 1908 | Build Power Line | (14, 22) | - | failed |
| 1908 | Build Power Line | (16, 22) | - | failed |
| 1908 | Build Power Line | (17, 22) | - | failed |
| 1908 | Build Power Line | (18, 22) | - | failed |
| 1908 | build_road_line | - | $60 | success |
| 1908 | build_road_line | - | $10 | success |
| 1908 | build_wire_line | - | $65 | success |
| 1908 | build_wire_line | - | - | failed |
| 1908 | build_wire_line | - | $35 | success |
| 1908 | build_wire_line | - | $15 | success |
| 1908 | build_wire_line | - | $190 | success |
| 1908 | build_wire_line | - | - | failed |
| 1908 | build_wire_line | - | $200 | success |
| 1908 | build_wire_line | - | - | failed |
| 1908 | build_wire_line | - | - | failed |
| 1908 | build_wire_line | - | - | failed |
| 1908 | build_wire_line | - | $40 | success |
| 1908 | build_wire_line | - | - | failed |
| 1908 | build_wire_line | - | - | failed |
| 1908 | build_wire_line | - | - | failed |
| 1908 | Advance | 24 months | - | success |
| 1906 | Advance | 24 months | - | success |
| 1904 | batch | - | $50 | partial |
| 1904 | Advance | 12 months | - | success |
| 1903 | Advance | 12 months | - | success |
| 1902 | Advance | 12 months | - | success |
| 1901 | Advance | 6 months | - | success |
| 1900 | Build Fire Station | (20, 47) | $500 | success |
| 1900 | Build Police Station | (26, 47) | $500 | success |
| 1900 | Advance | 6 months | - | success |
| 1900 | Advance | 3 months | - | success |
| 1900 | build_road_line | - | $50 | success |
| 1900 | build_road_line | - | $60 | success |
| 1900 | build_road_line | - | $10 | success |
| 1900 | build_road_line | - | $60 | success |
| 1900 | build_wire_line | - | - | failed |
| 1900 | build_wire_line | - | $5 | success |
| 1900 | build_wire_line | - | $15 | success |
| 1900 | build_wire_line | - | $20 | success |
| 1900 | build_wire_line | - | $110 | success |
| 1900 | build_wire_line | - | $110 | success |
| 1900 | build_wire_line | - | $30 | success |
| 1900 | build_wire_line | - | $110 | success |
| 1900 | build_wire_line | - | $85 | success |
| 1900 | build_wire_line | - | - | failed |
| 1900 | build_wire_line | - | $80 | success |
| 1900 | build_wire_line | - | $80 | success |
| 1900 | build_wire_line | - | $80 | success |
| 1900 | build_wire_line | - | - | failed |
| 1900 | build_wire_line | - | - | failed |
| 1900 | build_wire_line | - | $85 | success |
| 1900 | build_road_line | - | $170 | success |
| 1900 | build_road_line | - | $170 | success |
| 1900 | build_road_line | - | $170 | success |
| 1900 | build_road_line | - | $170 | success |
| 1900 | build_road_line | - | $170 | success |
| 1900 | build_road_line | - | $170 | success |
| 1900 | build_road_line | - | $170 | success |
| 1900 | build_road_line | - | $170 | success |
| 1900 | batch | - | $1,200 | success |
| 1900 | batch | - | $1,200 | success |
| 1900 | batch | - | $100 | partial |
| 1900 | batch | - | $1,000 | success |
| 1900 | batch | - | $900 | success |
| 1900 | Zone Residential | (23, 8) | $100 | success |
| 1900 | Bulldoze | (22, 7) | $10 | success |
| 1900 | Zone Residential | (23, 8) | - | failed |
| 1900 | Zone Residential | (23, 8) | - | failed |
| 1900 | batch | - | $295 | partial |
| 1900 | build_wire_line | - | $100 | success |
| 1900 | build_wire_line | - | $90 | success |
| 1900 | build_wire_line | - | $90 | success |
| 1900 | build_wire_line | - | $100 | success |
| 1900 | Build Coal Power | (20, 24) | $3,000 | success |
Population 8,720
Funds $3,929
Year 1911
Score 421
Class Town
Approval
Demand
Population Breakdown
Residential 236
Commercial 10
Industrial 15
Assessed Value
Value $8,835,000
Top Problems
Infrastructure
1 Police
1 Fire
2 Power
0 Ports
0 Airports
0 Stadiums
167 Roads
0 Rail
Power
Powered / Total 49 / 51 (96%)
Budget
Tax Rate 7%
Cash Flow $0
Fire 100%
Police 100%
Road 100%
Environment
Crime 20
Pollution 68
Land Value 100